Delivering a Multi-Level Logistics Facility for a Leading Aviation and Logistics Operator

Services
No items found.
solutions
No items found.
Industry
Automotive
Year
2023
Location
Bengaluru

Overview

A leading aviation and logistics operator partnered with Vestian to develop a 350,000 sq.ft. multi-level logistics park at Kempegowda International Airport, Bengaluru,designed to support high-capacity cargo, warehousing and associated operations.

Moving beyond a conventional industrial format, the facility was planned to accommodate heavy-loadwarehousing vertically, integrating bonded warehouses, offices, a cafeteria,utilities and supporting logistics infrastructure within a single campus. Thedevelopment incorporates racking systems ranging from 4 m to 10 m, supported bystructural systems designed for heavy loads, while a 30 ft.-wide ramp enablesefficient operational access to the upper-level warehouse.

As the Project Management Consultant, Vestian coordinated structural, civil, landscape, pre-engineered building, MEP and logistics planning disciplines to bring thecomplex development together. Sustainability and utility infrastructure wereintegrated into the overall planning through a 40 KLD sewage treatment plantand 400 cu. m rainwater storage tank.

A leading aviation and logistics operator partnered with Vestian to develop a multi-level logistics park at Kempegowda International Airport, Bengaluru, to support itsgrowing operational requirements.

The facility integrates bonded warehouses, office spaces, a cafeteria, utilities, andsupporting logistics infrastructure within a single campus. Vestian was appointed as Project Management Consultant, coordinating structural, civil,landscape, pre-engineered building, MEP, and logistics planning disciplines.

Designed for high-capacity warehousing, the facility incorporates vertical racking systemsranging from 4 m to 10 m, a 30 ft.-wide ramp providing access to theupper-level warehouse, and structural systems capable of supporting heavy-loadoperations. Sustainability measures include a 40 KLD sewage treatment plant anda 400 cu. m rainwater storage tank.

‍

350K
Square Foot Logistics Park
400 CU. M
Rainwater Storage Capacity
Multi-level High-Capacity Warehouses

Challenge

The project presented a combination of site, regulatory and execution complexities. Monsoonconditions affected excavation and other ground-dependent activities, whilerevised regulations introduced an additional approval process. As the sitefalls within the airport development area, excavation required necessarystatutory approvals, necessitating close coordination with BIAL and therelevant authorities before works could progress.

Limited space at site also required careful management of material storage and movement, while proximity to the airport meant craneoperations were subject to a specific NOC before commencement of activities.  

At the execution level, integrating structural, civil, MEP and pre-engineered building systems alongside evolving design requirements and long-lead materials demanded continuous coordination between design, procurement and construction. The initial reliance on a single-vendor procurement strategy added further program risk, with potential material delays directly affecting dependent activities and the overall construction sequence.

‍

Solution

The project required an agile delivery strategy as site, regulatory and procurementchallenges evolved through construction. To navigate the monsoon, criticalactivities were re-sequenced and a natural-slope earth collection pit wasintroduced to manage rainwater and maintain workable site conditions.Excavation progressed following close coordination with BIAL and the relevantauthorities to secure the required BIAPPA approval, while crane operations wereplanned around airport regulations and the necessary NOC.

Similarly, material storage and movement were carefully planned to maintain efficient construction flow. At the same time,structural, civil, MEP and pre-engineered building systems were closely alignedwith evolving design and long-lead procurement requirements.

To strengthen program control, the procurement strategy transitioned to an EPC model, integrating design, procurement and construction under a unified framework.  More than 186,000 safe man-hours went intocompleting the logistics park, bringing together high-capacity warehousing andintegrated supporting infrastructure.

‍

Key Services

Project Management
Every construction phase stays under direct oversight from our project managers, who maintain governance, reporting, and coordination from permits through occupancy.