Building a Future-Ready Workplace for a Leading Technology Platform

Services
No items found.
solutions
No items found.
Year
2025
Location
Bengaluru

Overview

A leading Southeast Asian technology platform partnered with Vestian to develop a 45,000 sq. ft. workplace inBengaluru as part of its growth and expansion strategy. The facility wasenvisioned as a modern, technology-enabled environment designed to supportcollaboration, innovation and employee engagement, with the entire workplacerequired to be delivered within an ambitious 80-day program

Vestian was appointed as the Integrated Service Delivery partner, coordinating design, construction, procurement, andstakeholder management to deliver the workplace within an accelerated program.

‍

45K
Square Foot Workspace
49,540
Achieved safe man-hours
80 Days
Delivery TImeline

Challenge

The project required delivering a design-led workplace within a stringent 80-day timelinewhile managing several technical and operational complexities. Limited ceilingclearance created challenges in routing MEP services without compromising theintended workplace design.

Extended lead times for select materials and dependencies on approvals for graphics, loosefurniture, and signage added pressure to the timeline. Maintaining alignmentacross design, procurement, and construction was critical to ensuringuninterrupted progress.

‍

Solution

Vestian adopted a structured execution approach focused on planning, stakeholder coordination,and project governance. MEP layouts and service routing were optimised toaccommodate building services within the restricted ceiling space whilepreserving the design intent.

Early procurement planning and suitable material alternatives helped mitigatelead-time risks, while regular coordination with stakeholders, consultants, andvendors accelerated approvals and decision-making. Continuous site monitoringand proactive issue resolution maintained progress throughout execution.

The project was completed within the planned 80-days, achieving 49,540 safe man-hourswith zero lost-time incidents.

‍